Progress Summary: November 01 to November 30, 2022 

  • Capitol Pavement of DC Inc. received approved 120-day time extension. Construction activities are on hold due to delay in the delivery of the traffic control cabinets.

  • All underground work, streetlight traffic signal and traffic cabinets foundations, streetlight and signal poles have been completed.

  • Installation of overhead hardware for streetlight and traffic signal have been completed.

  • Street light cable installation has been completed

  • Traffic signal cable installation have been completed.

  • Cable splicing in the mainline has been completed.

  • Installation of streetlight and traffic signal cables have been completed.

  • Fiber optic cable installation has been completed

  • 50 Pair communication cable installation has been completed.

  • 100 Pair installation has been completed.

  • Work on streetlight conductor cable for twin 20 has been completed.

  • Traffic fixtures installation have been completed.

  • Milling and paving on Pennsylvania SE EB and WB have been completed.

  • Jaxson Point spliced traffic signal cable for TEC power at Pennsylvania Ave SE from 3rd Street to 10th Street intersections as requested by DDOT.

  • Jaxson Point spliced Traffic Control Special Item DDOT Standard Modular Fiber Termination at Pennsylvania Ave SE intersections from 2nd Street to 14th Street

  • Mayor Work Left:

    • Electrical:

      • Traffic Control Cabinets: Delivery date is on hold until further notice

    • ​Civil Work:

      • Removal of existing SL, TS, and their foundations that will be completed after traffic cabinet installation

      • Sidewalk repair that will be completed after traffic cabinet installation

  • All TTC Signs at WZ have been inspected to ensure compliance.

  • Inspected all Tree Protection wire fencing installation for compliance along Pennsylvania Ave. SE from 2nd St. to 14th St. EB and WB.