REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
NOVEMBER 2022








Progress Summary: November 01 to November 30, 2022
-
Capitol Pavement of DC Inc. received approved 120-day time extension. Construction activities are on hold due to delay in the delivery of the traffic control cabinets.
-
All underground work, streetlight traffic signal and traffic cabinets foundations, streetlight and signal poles have been completed.
-
Installation of overhead hardware for streetlight and traffic signal have been completed.
-
Street light cable installation has been completed
-
Traffic signal cable installation have been completed.
-
Cable splicing in the mainline has been completed.
-
Installation of streetlight and traffic signal cables have been completed.
-
Fiber optic cable installation has been completed
-
50 Pair communication cable installation has been completed.
-
100 Pair installation has been completed.
-
Work on streetlight conductor cable for twin 20 has been completed.
-
Traffic fixtures installation have been completed.
-
Milling and paving on Pennsylvania SE EB and WB have been completed.
-
Jaxson Point spliced traffic signal cable for TEC power at Pennsylvania Ave SE from 3rd Street to 10th Street intersections as requested by DDOT.
-
Jaxson Point spliced Traffic Control Special Item DDOT Standard Modular Fiber Termination at Pennsylvania Ave SE intersections from 2nd Street to 14th Street
-
Mayor Work Left:
-
Electrical:
-
Traffic Control Cabinets: Delivery date is on hold until further notice
-
-
Civil Work:
-
Removal of existing SL, TS, and their foundations that will be completed after traffic cabinet installation
-
Sidewalk repair that will be completed after traffic cabinet installation
-
-
-
All TTC Signs at WZ have been inspected to ensure compliance.
-
Inspected all Tree Protection wire fencing installation for compliance along Pennsylvania Ave. SE from 2nd St. to 14th St. EB and WB.