REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
JULY 2022








Progress Summary: July 01 to July 31, 2022
-
Capitol Paving of DC. Inc. continued construction activities on Pennsylvania Ave SE, between 2nd street and 14th street, for the installation of streetlight, traffic signals and incidentals work.
-
The work hours are 9:30 am to 3:30 pm—Monday to Friday. During milling and paving operations, the following hours apply: EB 08:00 am to 4:00 pm; WB 9:00 am to 7:00 pm; Saturdays 08:00 am to 5:00 pm.
-
The contractor has set up and placed the approved MOT signs before starting the daily construction activity, They are inspected for compliance.
-
Street parking is restricted in the work zone, and a temporary travel-lane closure begins at 9:30 am. (Except during milling and paving operations). At the end of each workday, temporary signs and traffic control devices are removed to allow traffic to operate in normal conditions.
-
Tree guards are installed for the protection of the trees.
-
Plastic barrier fences are used on the sidewalk side, and drums are on the roadway for the safety of the pedestrians, bicycle, and vehicular traffic.
-
The full width of the sidewalk is available for pedestrians and businesses during construction.
-
Flaggers are assigned to assist the pedestrians and vehicular traffic at the intersection(s).
-
All underground work, streetlight traffic signal and traffic cabinets foundations, streetlight and signal poles have been completed.
-
Installation of overhead hardware for streetlight and traffic signal is in progress, completed up to 12 th Street.
-
Street light cable installation has been completed
-
Traffic signal cable installation has been completed
-
Cable splicing manholes have been completed, except at each intersection for the traffic cabinet installation
-
Feed between PEPCO manholes and manholes has been completed. PEPCO needs to energize.
-
#4 and #2 cable installation has been completed
-
Fiber optic cable installation has been completed
-
50 Pair communication cable installation has been completed
-
100 Pair installation has been completed
-
The major work left to perform:
-
Electrical Work:
-
Cable splicing 5 manholes left
-
Feed between PEPCO and manholes PEPCO, that needs to energize.
-
Overhead fixtures from 12th Street to 13th Street to complete
-
Cabinet installation.
-
-
Civil Work:
-
Removal of existing Streetlight and traffic signals and their foundations o Sidewalk repair o Punch list
-